Website Development Cost: Company Profile vs Web App
Website development cost in IDR: a company profile at 8–90 million, a web app at 150–400 million, a line-by-line quote and the monthly cost after launch.
Website development cost (biaya pembuatan website in Indonesian) depends far more on what the site does than on how many pages it has: a company profile runs IDR 8–90 million, and a web app runs IDR 150–400 million. The two can look alike on screen, which is why two quotes for “a website” can differ by a factor of ten.
I’m Aditya S, Business Development Manager at Synetica, a tech-based business consultancy combining strategy and execution for Dreamers and Growing Businesses. This guide prices two fictional quotes line by line so you can check every number. The figures are teaching assumptions, not Synetica prices, vendor quotes or a market survey.
You’ll get the price ranges, a line-by-line comparison of a company profile and a web app, the factors that move the price, the cost after launch, a payment schedule and the red flags in a quote.
TL;DR — the whole guide in five lines
- Price the type, not the page count: a company profile is IDR 8–90 million and a web app is IDR 150–400 million.
- A web app costs five times a company profile in our example: IDR 230 million against 46 million at the same day rate.
- Most of a web app’s price is unseen: back-end, integrations and testing are 130 of the 230 million, or 57%.
- Budget the monthly cost too: running the web app for three years adds IDR 180 million, 78% of its build fee.
- Pay for deliverables: 30% for a signed scope, 40% for a working staging link, 30% at handover.

What is included in website development cost?
Website development cost covers six kinds of work: planning, design, front-end, back-end, testing and launch. A company profile needs very little back-end. A web app needs a lot of it.
- Planning. The brief, sitemap, user flows and written scope.
- Design. Page layouts, the visual style and the phone version.
- Front-end. The pages a visitor sees and clicks.
- Back-end. The database, logins, user roles, business rules and connections to other systems.
- Testing. Checks on phones and browsers, plus security and load checks for a web app.
- Launch. Hosting setup, domain, analytics, redirects and handover of access.
Three items usually sit outside the quote: copywriting and photos, the domain and hosting fees, and maintenance after launch. Ask whether each one is in or out.
How much does website development cost in Indonesia?
Plan for IDR 8–25 million for a template company profile, 35–90 million for a custom one, and 150–400 million for a web app.
| Package | Scope | Estimate (IDR) | Timeline | Best for |
|---|---|---|---|---|
| Template company profile | 5–8 pages, ready-made theme, CMS, contact form | 8–25m | 2–4 weeks | A business that needs a credible address online |
| Custom company profile | Custom design, CMS, SEO basics, analytics | 35–90m | 6–8 weeks | A business that relies on the site for leads |
| Web app | Login, roles, payments, integrations, dashboard | 150–400m | 10–16 weeks | A business process that runs inside the site |
These are the same planning ranges we use in the website development services guide, which covers how to choose the vendor. This article goes one level down, into the lines of the quote.
If you would rather build a simple site yourself, the guide to creating a website puts that route at about IDR 9.9 million in cash over three years.
Why does a web app cost five times a company profile?
A web app costs more because most of its work happens behind the screen, where the visitor never looks. Here is the proof, using one fictional catering company and two quotes at the same rate of IDR 2 million per person-day.
Quote A is a custom company profile: eight pages, a menu, a gallery and a contact form. Quote B is an ordering portal: customers log in, place an order and pay, and staff manage orders in a dashboard.
| Line, IDR million | A. Company profile | B. Web app |
|---|---|---|
| Planning (brief or blueprint) | 4 (2 days) | 20 (10 days) |
| Design | 12 (6 days) | 30 (15 days) |
| Front-end | 16 (8 days) | 50 (25 days) |
| Back-end, database, roles | 0 | 70 (35 days) |
| CMS setup or integrations | 8 (4 days) | 24 (12 days) |
| QA, security, launch | 6 (3 days) | 36 (18 days) |
| Total | 46 (23 days) | 230 (115 days) |
Quote B takes 115 days against 23, so it costs exactly five times as much. The day rate is the same.
Where does the extra IDR 184 million go?
Back-end, integrations and testing make up IDR 130 million of the web app, or 57% of the quote. None of that work appears in a design mock-up. In the company profile, design and front-end are 28 of 46 million, or 61%, so most of what you pay for is visible.
That is the iceberg in every web app quote. When two vendors differ by IDR 100 million, the gap is almost always below the waterline: one of them has priced roles, payment failures and security testing, and the other has not.
Testing is not padding. The OWASP Top 10, a widely used list of web application security risks, ranked broken access control first in its 2021 edition. See the OWASP Top 10. A site with logins has to be tested for exactly that: one customer opening another customer’s order.
Company profile or web app: which one are you pricing?
You are pricing a web app if visitors log in, pay or book, or if the site exchanges data with another system. One yes is enough.
- Do visitors log in? Accounts need a database, password resets and access rules.
- Does the site take payments or bookings? Each needs a payment gateway and handling for failed or duplicate transactions.
- Does data sync with another system? Stock, prices or orders that come from a POS or accounting system need an integration.
- Must the design win leads? If the first three answers are no, this one separates a custom company profile from a template.
A catalogue with a WhatsApp button is still a company profile. It becomes a web app the day customers check out on the site.
If you answered yes but are unsure the feature is worth it, test it before you build it. Our MVP guide explains how to test one risky flow with a small first version.
Validate it in 2 weeks. Before you spend heavily on website development, Blueprint & Prototype tests your assumptions: a spec, a clickable prototype in front of real users, and a real cost estimate. The two-week promise covers prototype validation; it does not mean the finished site ships in two weeks.
What factors determine website development cost?
Features that add rules, roles or connections move the price. Extra pages barely do. At our assumed IDR 2 million a day, these are typical additions:
| Factor | Typical addition | Why it costs that |
|---|---|---|
| A second language | 3–5 days, IDR 6–10m | Every page, form and email exists twice |
| Each extra user role | 4–6 days, IDR 8–12m | New screens, access rules and tests |
| Payment gateway | 5–8 days, IDR 10–16m | Failed, pending and refunded payments all need handling |
| Admin dashboard and reports | 8–12 days, IDR 16–24m | Filters, exports and totals that must reconcile |
| Integration with POS or accounting | 8–15 days, IDR 16–30m | Two systems must agree on every record |
| Data migration | 5–10 days, IDR 10–20m | Old data is cleaned, mapped and checked |
Ten extra content pages on a CMS add a day or two. One extra user role adds a week.
To lower the price, cut scope and keep the day rate. In quote B, moving online payment to a second release removes about 8 days, or IDR 16 million, and you still learn whether customers order online. A cheaper rate on the same vague scope only moves the cost to later.
If the app stores customer data, Indonesia’s Personal Data Protection Law (Law No. 27 of 2022) also applies, which is one more reason the security line belongs in the quote. For app-sized budgets, the application development cost guide breaks the estimate into seven budget lines.
What does a website cost after launch?
In our example the company profile costs IDR 0.5 million a month to run and the web app costs IDR 5 million a month. The build fee is the price of the car. The monthly cost is the fuel and servicing.
| Three-year component, IDR million | Company profile | Web app |
|---|---|---|
| Build fee | 46 | 230 |
| Hosting, domain and services | 7.2 (0.2 a month) | 72 (2 a month) |
| Care, fixes and support | 10.8 (0.3 a month) | 108 (3 a month) |
| Three-year total | 64 | 410 |
Running the web app for three years costs IDR 180 million, which is 78% of its build fee. For the company profile the figure is 18 of 46 million, or 39%.
So a quote of IDR 230 million is a three-year commitment of 410 million. New features after launch are extra. Ask every vendor for the monthly figure in writing, next to the build fee.
How do you compare website quotes and choose a partner?
Give every vendor the same written brief, then compare the lines below the waterline. A quote that is one number for “website” cannot be compared with anything.
- Ask for person-days per line. Planning, design, front-end, back-end, integrations and testing.
- Check that testing has its own line. If it is missing, it is either hidden or not happening.
- Ask what is excluded. Content, hosting, payment gateway fees and maintenance are the usual gaps.
- Confirm ownership. Domain, code, hosting account and design files in your name.
- Get the monthly cost. Hosting and support, with response times.
A freelancer suits a template site, an agency suits a stable brief, and a product studio suits a web app whose goal is still unproven. Our software house guide gives five checks for the partner itself.
What is the timeline, and when should you pay?
Our company profile takes 6 weeks and the web app takes 10, and each has three payments tied to something you can open and test.
| Milestone | What you receive | Company profile | Web app |
|---|---|---|---|
| Scope signed, 30% | Sitemap, prototype, fixed scope | 13.8m, week 1 | 69m, week 2 |
| Staging link, 40% | The working site on a test address | 18.4m, week 5 | 92m, week 8 |
| Handover, 30% | Launch, access, documentation | 13.8m, week 6 | 69m, week 10 |
The web app schedule follows Synetica’s own path: 2 weeks of Blueprint & Prototype, then about 8 weeks of Production Grade Software. Larger scopes take longer, up to the 16 weeks in the range above.
No deliverable, no payment. A vendor who asks for 70% before showing a staging link is asking you to carry their risk.
What are the red flags in a website development quote?
A quote is a warning sign when it hides the work, the owner or the monthly cost. Watch for these six:
- One line, one number. Nothing to compare and nothing to hold anyone to.
- No testing line. Bugs become your customers’ job to find.
- “Unlimited revisions”. It usually means the scope was never written down.
- Domain and hosting in the vendor’s name. Leaving later costs you your address.
- No monthly figure. The cost after launch arrives as a surprise.
- A web app at a company profile price. At IDR 2 million a day, 30 million buys 15 days. Quote B needs 115.
A very cheap web app quote is rarely a bargain. More often the vendor has priced only the part above the waterline.
What I would do before approving a website budget
Decide the type first, then ask for the lines. Most budget surprises come from approving “a website” without saying which kind.
- No login, no payment, no sync: it is a company profile. Start with a template unless the design must win leads.
- One yes on the three questions: it is a web app. Budget the build fee and three years of running cost together.
- Unsure the feature is worth it: prototype the riskiest flow before you pay for the back-end.
This advice fits Growing Businesses moving a process online and Dreamers pricing a first product. If all you need is a page with your address and a WhatsApp button, you do not need a quote at all yet.
My next step would be to book a scoping conversation with your answers to the three questions and the features you think you need.
FAQ — Website development cost
How much does website development cost?
As planning ranges, IDR 8–25 million for a template company profile, 35–90 million for a custom company profile and 150–400 million for a web app with login, payments or integrations. Real quotes depend on the written scope.
How much does a company profile website cost?
In our fictional example a custom eight-page company profile costs IDR 46 million for 23 person-days, plus about IDR 0.5 million a month to run. A template version costs IDR 8–25 million.
How long does website development take?
About 2–4 weeks for a template company profile, 6–8 weeks for a custom one and 10–16 weeks for a web app. Late content delays company profiles most often. Unclear scope delays web apps.
What is the difference between a software house and a freelancer?
A freelancer is one person, which is fast and cheap for a template site but leaves continuity uncertain. A software house brings a team with design, back-end and testing roles, which a web app needs.
What is included in website development cost?
Planning, design, front-end, back-end, testing and launch. Copywriting, photos, domain and hosting fees, payment gateway fees and maintenance after launch are often excluded, so ask about each one.
Related Posts
Aditya S
Business Development Manager, Synetica.
Put it into practice
Need help putting this into practice?
We turn the ideas in this article into a prototype tested with real users in 2 weeks (from Rp49jt)—or production-grade software in 8 weeks (from Rp100jt).